Elixir Energy Limited (“Elixir” or the “Company”) is pleased to provide an update on the Daydream-2 program in its 100% owned Grandis Project in Queensland’s Taroom Trough.

HIGHLIGHTS

Final equipment being mobilised to siteMilling of plug set above the Lorelle Sandstone due over the weekendFlow testing of the stimulated Lorelle to follow immediately after

Elixir is in the final stages of mobilizing all equipment for the Daydream-2 stimulation and testing program. Over the coming weekend the plug set above the Lorelle Sandstone is due to be milled out and post stimulation flow testing of the Lorelle sandstone will follow immediately after. Given the depth and high pressure of this well, Elixir has been undertaking additional HSE inspections to ensure the simulation and testing will be conducted smoothly and safely.

The Coil Tubing Unit (CTU) which was recently imported from New Zealand has been checked and function tested in cooperation with Elixir’s neighbouring Taroom Operator. The CTU is required to remove the plug above the Lorelle Sandstone before the flow test can commence.

The wellhead manifold and “Christmas Tree” valves have been serviced and pressure tested to 13,000 psi. They are fully functional and ready for tie in to the stimulation spread.

In excess of 815,000 pounds of proppant and micro-proppant is also being transported to the wellsite in preparation for the 5 remaining stages of stimulation that will follow the Lorelle flow test.

Click here for the full ASX Release